October 26, 2021

Campus Construction October Update: Golisano Community Engagement Center

GCEC Construction

Were you wondering about the progress on the new Golisano Community Engagement Center? Construction is in full swing and the crews are moving forward. When people walk or drive by, they can begin to visualize the building.

Highlights from the last month include:

  • Elevator and stair tower block has been completed
  • Building foundations have been completed.
  • Electrical and plumbing have been roughed in in the two story section.
  • Sections of the exterior wall block have been completed.
  • The new access road is underway! This road will connect Westside Drive to the Davison parking lot. Traffic can enter from Westside Drive and continue through to exit from Nelson Morton Drive and vice versa.

Where is the building located?

The Golisano Community Engagement Center will face Westside Drive, be in front of Beeson Apartments and is positioned just west of the pathway to North Campus residential buildings. This building will be easily accessible from Westside Drive.

Click here for more information on the Connect the Community campaign.