Coming Together

May 6th, 2008

2008-05-06 008.jpg

Roof trusses going up on the rear entrance canopy.

As painters apply finish coats of paint the ceiling tile, light fixtures, vents and sprinkler heads are going in on both levels. Most spaces inside have glass installed in interior windows. Once done, a final cleanup of the interior and then doors and carpeting can be installed. Exterior painting, walks and entrances are being finished. Projected move in for Teacher Ed and Business is mid June.

Click here to go to our photo gallery

Â

The light at the end of the tunnel

April 22nd, 2008

2008-04-22 006.jpg

Ceiling tile and vent in a second floor office

A lot has been accomplished in the week since the last update. Final coats of paint are being applied to second floor walls. Where the painting is done, ceiling tile and vents, electrical fixtures, smoke detectors, etc. are being installed.  Exit signs are up, window glass is being installed in interior windows and emergency strobes and sirens are going in. Workers are finishing the dry wall taping and mudding on the lower level which will lead to painting, etc. With the early spring weather exterior painting has begun.

Click here to go to our photo gallery

April 15th, 2008

2008-04-15 004.jpg

Grid work for ceiling tile in a second floor office.

Workers have been painting on the second floor and ceiling tile grid work is being installed as each space is finished. Mudding and taping have been proceeding on the first floor where painting will soon start. The new canopy for the rear entrance is taking shape.

Click here to go to our photo gallery

Finish work begins.

April 7th, 2008

2008-04-07 004.jpg

Boxes of drop ceiling gridwork waiting to be installed.

With the majority of the dry wall installed workers have begun painting on the east side of the second floor as others finished taping and mudding on the west side of the same floor.  Grid work can begin for the drop ceilings as the paint work is completed. Next up workers will move to the lower level to finish taping and mudding to be followed by painting there. Still to come are fixtures (lighting, plumbing, ventillation, etc.), inside windows and doors and floor treatments.

Click here to go to our photo gallery

March 31st, 2008

2008-03-26 014.jpg

Design detail in the main hallway of the second floor

Workers have been busy since the last update with sheet rock nearly all installed and seams taped and plastered. The next step will be a slurry coat then primer and paint. With warmer weather permitting, the soffitts are being installed on the exterior of the building and the archway in the lower entrance is receiving its brickwork. Boilers and other plumbing are in place in the boiler room and service panels for electricity are being installed and wiring from throughout the building to the terminal room for the network has been installed. As each week passes the final shape of the interior becomes more evident.

Click here to go to our photo gallery

Rapid progress

March 26th, 2008

2008-03-26 017.jpg

View of Golisano Library from second floor office.

A new larger water main was connected today to supply the needs of the Hastings Center. Work progresses on the installation of dry wall and many offices and classrooms are taking shape. Workers are installing insullation on pipes which will carry heated/chilled water to air handlers at various locations throughout the building. Support columns for the rear entry canopy are being erected and the permanant  entry doors are being installed on both levels.

Click here to go to our photo gallery

Dry wall installation begins

March 18th, 2008

2008-03-18 009.jpg

Drywall going up on the second floor.

Workers have begun the big job of installing insulation and drywall on the second floor of Hastings Center. As the work progresses it becomes easier to visualize the finished facility. The footers for the rear entrance canopy are also in place and workers continue to install heating and air conditioning equipment and ductwork and wiring.

Click here to go to our photo gallery

Work continues on plumbing,wiring and ductwork

March 10th, 2008

2008-03-10 009.jpg

Footer for the new rear entrance to the lower level

In addition to work to complete ductwork, plumbing and wiring that will be hidden when dry wall installation begins, workers have poured the footers for the rear entrance canopy on the lower level. Door and window frames are nearly all installed and insulation has been placed on some external walls on the second level.

Click here to go to our photo gallery

Major changes but still the same

March 3rd, 2008

2008-03-03 001.jpg

Second floor archway carries the roof profile inside.

With the framing nearly complete workers have been installing door and window frames for the inside offices and classrooms. When completed the vaulted ceiling that was a main feature in the old library will be covered up except in some areas. Interior archways will carry the roof line inside the newly renovated building.  Work will begin this week to install a larger water main to the building to supply the needs of the occupants and footers for the new entrance canopies.

Click here to go to our photo gallery

Framing begins on lower level

February 25th, 2008

2008-02-25 001.jpg

Framing inside the entrance to the lower level and hallway to front main stairwell.

Workers have finished installing the windows which allows the building to be closed to the elements.  Roof top air conditioning units were placed last week and framing is taking shape on the lower level. With framing in place there is a sense of placement  of offices and classrooms.

Click here to go to our photo gallery